CLIENT: MACTEC, INC.
October 2002: Structure
INTEGRITY TESTING OF DRILLED PILES FOR TALL BUILDINGS
Tall buildings have inherently large foundation loads. If soil conditions are
not suitable to support footings, either due to insufficient bearing capacity
or excessive settlement, pile foundations are necessary. Drilled piles are
frequently used to support tall buildings. If unfavorable soil conditions are
present, drilled pile foundations will likely require the use of shell casings
and/or drilling mud. In these cases, direct observation of the drilled pile
shaft is not possible and, therefore, other means to evaluate the adequacy
of the piles may be required. Since tall buildings will have higher foundation
demands, including higher seismic overturning forces, integrity of the pile
foundations is critical.
Several non-destructive testing methods may be employed to evaluate the
adequacy of drilled piles (and other structural members constructed using
similar techniques). Some of these methods include sonic testing of piles by
seismic echo, impulse response, cross-hole sonic logging, and density
testing by downhole gamma-gamma logging. General criteria for
acceptance of piles for the various test methods are available.
In addition to the specific test methodology, a major part of the integrity
testing procedure is the determination of the appropriate level of testing
required.
Non-Destructive Testing Methodology
Non-destructive testing methods can generally be separated into two
categories: 1) methods that require access for equipment within the pile,
and 2) methods that rely on external excitation of the pile and utilize wave
propagation relationships to estimate physical pile characteristics.
The first category of includes gamma-gamma logging (GGL) and
cross-hole sonic logging (CSL). These methods each require access for
probes to be inserted within the pile. The second category includes sonic
echo (SE) testing and impulse response (IR) testing, and can be employed
where access to the top of the pile is available without the use of tubes
within the piles.
Each of these methods provides results immediately. However,
interpretation of test results by the engineer and determination of mitigation
measures (if necessary) require adequate time.
Downhole Gamma-gamma Logging (GGL)
GGL testing provides a means to evaluate the consistency of a drilled pile
shaft by giving an estimate of the bulk density of the concrete. GGL is
typically performed within PVC tubes that are pre-installed to the
steel-reinforcing cage of cast-in-drilled-hole (CIDH) piles. In cases where
the testing is not initially planned, GGL can be performed within holes
cored in the pile. In general, the tubes (or cored holes) should be located at
least two inches from longitudinal reinforcement, as the density of the
reinforcing steel will affect the results of the logging.
Depending on the intensity of the source and the spacing between the
source and receiver, GGL can evaluate the density of the concrete for a
radial distance of about 2 to 3 inches using a low-energy source, and 6 to
8 inches using a high-energy source. Typically, several tubes are installed in
the piles to allow multiple readings. Several public agencies, including the
California Department of Transportation (CALTRANS), recommend one
access tube per foot of pile diameter.
The results are reported on a density versus depth plot. The plot typically
indicates the mean density and mean plus one, two and three standard
deviations. CALTRANS has suggested that acceptance criteria for axially
loaded piles could be based on the measured density of the concrete being
greater than the mean density minus three standard deviations.
GGL Limitations
A major limitation is that radiation sources are subject to Nuclear
Regulatory Commission (NRC) regulations, including special training and
licensing for handling and transporting the devices. Because of the
radioactive source in the probe, the probe cannot be left in the pile.
Retrieval and recovery of the probe can be very costly. In one instance,
two weeks of effort was required to retrieve a probe lodged in an access
tube.
Blockages of the access tubes can occur, limiting the depth to which the
probe can be advanced. The length of the probe limits measurements to
approximately below the upper 18 to 24 inches and above the lower 18 to
24 inches of the PVC tubes. If the access tubes are too close to the
longitudinal reinforcement, the higher density of the steel will affect the
results.
Whether or not PVC tubes are out of plumb after the pile is constructed
can also limit results. In some cases, PVC tubes can be pushed outward,
allowing the lesser soil density to affect the measurements. Finally, GGL is
relatively slow when compared with CSL and SE Testing.
Cross-Hole Sonic Logging (CSL)
CSL evaluates the uniformity and continuity of concrete by recording the
velocity of signals from an emitter to a receiver, each inserted into the pile
in preset tubes or pipes, typically Schedule 40 PVC pipe. Steel pipes can
also be used and, in fact, are preferred for CSL. If the concrete is
consistent and uniform, the velocity (wave travel time) at different depths
should be constant, assuming that the horizontal distance between the PVC
tubes (or steel pipes) is constant. Variations in the velocity indicate
irregularities in the concrete between the PVC tubes (or steel pipes).
Shortly before or after the concrete is placed, water is added to the access
tubes to allow transmission of the sonic signal from the tubes to the
concrete. When PVC tubes are used, the water will also help minimize the
effects of heat given off during the concrete curing, which can result in
de-bonding between the concrete and PVC tubes. De-bonding of the
PVC tubes from the concrete diminishes the quality of the downhole
logging to the extent that the logs may not be useful. Thus, steel tubes,
which are much more resistance to de-bonding effects, are preferred.
GGL cannot be performed if steel tubes are used. Downhole testing would
be limited to CSL in this case. Applying an anti-de-bonding agent to the
PVC tubing could also be employed to minimize the potential for
de-bonding. Typically, de-bonding of PVC tubes will occur about 7 to 10
days after the placement of concrete and after about 45 days in steel pipes.
Typically, one testing access tube is installed per each foot of pile diameter,
with a minimum of two tubes for piles less than 24 inches in diameter. For
larger piles, an added benefit is the ability to perform measurements
between different tubes, and thus pinpoint a defect. In addition, staggering
the depths of the transmitter and receiver can allow evaluation of different
travel paths, providing additional data for evaluation. This method is known
as CSL tomography.
CSL Limitations
Limitations include de-bonding of the PVC tubes after relatively short
times, the inability to evaluate the concrete not located between two tubes,
and the potential for blockages within the PVC tubes, limiting the depth to
which the probe can advance. In addition, the length of the probes limit
measurements to approximately below the upper 18 to 24 inches, and
above the lower 18 to 24 inches of the PVC tubes.
Sonic Echo (SE) Testing
SE testing is a relatively simple non-destructive pile integrity test method
that provides limited information. The principle of SE testing is that a
compression wave generated by a hand-held hammer blow at the top of
the pile will travel down the concrete pile shaft, and will be reflected at the
bottom of the pile shaft where there is a significant change in the physical
properties of the medium the wave is traveling through. Interpretation of
the test results is generally difficult and often inconclusive, particularly for
longer piles, as would be required for tall buildings.
Irregularities in the concrete, and/or increases or reductions in the pile shaft
section (bulging or necking), are identified by changes in the resistance
(impedance) to the traveling wave. Decreases in resistance indicate
necking, reduction in the density of elastic modulus of the concrete, or a
discontinuity in the pile. This will result in the wave echo received at the top
of the pile prior to the time computed for the wave to travel the full length
of the pile. Increases in resistance indicate increased cross sectional area,
or an increase in the elastic modulus or density of the concrete.
An increase in the impedance will be shown by displacement opposite that
of the displacement resulting from the hammer blow, where the pile is
socketed into rock that is much denser and thus transmits the compression
wave at a much higher velocity.
SE Testing Limitations
Minor defects generally are not detectable with SE testing. Recent studies
show that it is difficult to determine defects that are less than about a
quarter of the wavelength, which is typically about 4½ feet (1.6 meters).
Therefore, defects less than about 15" are not detectable. Furthermore,
some studies indicate that defects representing less that 50 percent of cross
sectional areas are not detectable with sonic echo testing. As a result of the
limitations, false positive test results may not be uncommon.
In addition, the length of the pile that can be tested is limited due to
dissipation of the wave energy at the sides of the pile, resulting from friction
between the soil and the pile. Typically, SE testing is reliable for piles that
are less than about 30 times the pile diameter in length, although the range
may vary from about 20 to 40 times the pile diameter, depending on the
soil type.
Other limitations include the inability to evaluate the pile below a major
defect, and the inability to determine which side of the pile a defect occurs.
Impulse Response (IR) Testing
IR testing is generally similar to sonic echo testing, however, the hammer
used measures the force applied to pile head versus time. In addition, the
data from the wave traveling down the pile shaft and the data from the
hammer impact are processed using Fourier transform methods, resulting in
a more sophisticated analysis of the data.
The distance to the base of the pile or to a major defect can be inferred by
observing the increment of frequency between peaks, as this distance is in
proportion to the distance from the top of the shaft to the point where the
energy is being lost.
IR Testing Limitations
This method has the same general limitations as sonic echo testing,
however, the IR method provides results in a format that is somewhat
easier to interpret.
Evaluating the Need for Integrity Testing
Due to the sensitivity of each method, sonic echo test results may indicate a
sound pile, while GGL and/or CSL results indicate significant defects in the
same pile. Difficulty in interpreting SE and IR test results, due to variation in
input signal and influence of pile geometry and soil characteristics, is
especially true for longer piles that are typically required for tall buildings.
CSL and GGL test results generally do not correlate well, as each method
essentially tests a different portion of the pile section. Thus, sound CSL
results combined with poor GGL results could indicate an acceptable pile
when considering axial loading, however, could indicate an unacceptable
pile when considering lateral loading. As a result, it is necessary to select an
appropriate test program that will provide acceptable confidence levels for
the engineer, depending on the nature of the structure and the configuration
of pile groups.
If periodic testing of piles is appropriate, it is generally prudent to perform
testing on a pre-determined number of the initial piles. If the testing on the
initial piles indicates an acceptable confidence level in the method of pile
construction, and the contractor's execution of the construction methods,
the frequency of the testing may be reduced.
Conclusions
Several non-destructive test methods are available to evaluate the integrity
of drilled piles. These methods, when combined with proper geotechnical
monitoring and observation of pile drilling and construction process, can
provide confirmation of the adequacy of piles without performing more
costly full scale pile load testing.
CSL is the most effective for identifying significant defects in piles that carry
primarily axial loads. GGL is useful for evaluating the density in the outside
portion of the pile, but can provide little other information. SE testing is
useful for shorter piles that support less critical or sensitive structures. IR
testing provides a more sophisticated means of evaluating piles using
surface echo testing methods, however, is generally subject to the same
limitations of SE testing.
SE and IR testing are generally more economical than the downhole
methods of GGL and CSL. GGL is typically much slower to perform, and
thus more expensive than CSL, as it is necessary to allow more time to
properly record the backscatter.
Selection of the appropriate the test method is highly dependent on the
nature of the drilled pile, including the geometry, the soil type, and the
number of piles in a pile group. The time required for the engineer to
evaluate the test results, and the cost of the testing with respect to the
benefits should also be considered.